SCRUM Sprint 1: review, retro, and carry-over
Window: 2026-03-13 to 2026-03-27
Closed: 2026-04-01
Participants
- Dani Y.
- Codex-Agent
Sprint goal
Finish the preview deployment.
Planned
- Sprint goal: J01-9, J01-13, J01-16, J01-31
- Support: J01-93, J01-98
- Admin / frame:
J01-72 and
J01-94 as the public
sprint/mirror step under
J01-72
What actually happened
- Partial sprint-goal delivery: J01-16 was completed
- Support delivered: J01-93 and J01-98 were completed
- Admin/frame work delivered: J01-72, J01-96, J01-107, and J01-108 were completed
- The sprint contained 18 issues in total; 7 reached
done, 11 stayed open.
Not finished / Carry-over
- Open goal work: J01-9, J01-13, J01-31
- Open admin/frame work: J01-104, J01-109, J01-116
- Open unplanned add-on work: J01-105, J01-111, J01-113, J01-115, J01-117
Scope changes
- Additional work entered the sprint beyond the original planning: J01-96, J01-104, J01-105, J01-107, J01-108, J01-109, J01-111, J01-113, J01-115, J01-116, J01-117
- Five of them were explicitly marked as
sprint-unplanned:J01-105,J01-111,J01-113,J01-115,J01-117.
Review
- The sprint goal “Finish the preview deployment” stayed valid, but was only reached in part.
- Most core goal issues stayed open; only
J01-16was completed from the foursprint-goalissues. - At the same time, substantial support and admin work was delivered and improved the project operation and public traceability.
- The sprint therefore shows a real shift of focus between preview work and building a still-new project and Jira operating model, not a lack of work.
Retro
- Worked well:
- Support and admin work moved important Jira, mirror, and documentation foundations forward in a durable way.
- The sprint is no longer silently overdue; it is now closed cleanly in Jira and GitHub Pages.
- Missing:
- Most of the actual goal issues remained unfinished.
- Sprint planning was still too narrow for the real spread of work.
- Observed conditions:
- The project is still in a pre-preview phase, so operational focus shifts more easily than in a more stable product phase.
- Jira management with AI agents is still new, which made the operating overhead higher and less predictable.
- New unplanned work entered the sprint and had to stay visible.
- Special family visits and illness reduced the available work time.
- Consequence:
- Upcoming sprints need to be planned with more explicit tolerance for deviation in this phase instead of assuming a rigid goal width.
Risks
- Preview work and framework work still compete inside the same sprint.
- Carry-over from Sprint 0 must not silently displace the sprint goal again.