Window: 2026-04-01 to 2026-04-15
Status: active

Participants

  • Dani Y.
  • Codex-Agent

Sprint goal

Finish the preview deployment.

Deliberate carry-over from Sprint 1

  • The open goal issues from Sprint 1 are carried over deliberately: J01-9, J01-13, J01-31
  • They stay sprint-goal because Sprint 2 continues the same goal on purpose.
  • J01-105 is included as sprint-support because it explicitly blocks J01-9.

Sprint backlog

Sprint goal

Support

  • J01-105 — simplify the pipeline-spec manifest for a clear parameter flow

Admin / frame

  • J01-119 — harden the targeted Jira/pages sync against silent regressions
  • J01-120 — close Sprint 1 cleanly and publish review/retro
  • J01-121 — plan Sprint 2 and sort carry-over deliberately

Not taken in for now

  • Open leftovers from Sprint 1 remain in the backlog for now instead of being pulled into Sprint 2 silently: J01-104, J01-109, J01-111, J01-113, J01-115, J01-116, J01-117

Planning decision

  • Sprint 2 does not inherit every open Sprint-1 issue.
  • Admission is based on:
    • direct relation to the preview goal
    • explicit blockers of the goal work
    • follow-up work that is already actually in progress
  • This keeps the board manageable again even while the pre-preview phase still implies more variation than a mature product phase.

Risks

  • The three open goal issues from Sprint 1 remain substantial and still carry most of the preview risk.
  • J01-105 must actually help unblock J01-9; otherwise support work stays in the sprint without helping the goal.
  • Admin work must not displace the sprint goal again.
  • New unplanned work remains possible and must then be categorized visibly.